一、水泥纖維外墻掛板怎樣安裝
1、水泥纖維外墻掛板工藝流程
清(qing)理結(jie)構表面(mian)→結(jie)構上(shang)彈出垂直線→大角掛(gua)兩豎直鋼(gang)絲→結(jie)構鉆孔并插(cha)膨脹螺栓→鑲角鋼(gang)固定件(jian)→固定豎向方鋼(gang)管→連接橫(heng)向角鋼(gang)→連接橫(heng)向鋁龍骨→調節(jie)與固定→干掛(gua)纖維水泥壓力板(板材背面(mian)鋁掛(gua)件(jian)提前(qian)安裝(zhuang)完畢)→水平垂直度調整→面(mian)層清(qing)理(柱(zhu)部(bu)位嵌板縫密封(feng)膠)
2、工地收貨
收貨要設專人負責管理(li),要認真檢查材(cai)料的(de)規格、型號是否真確、與料單是否相(xiang)符(fu)。發現纖(xian)維(wei)(wei)水(shui)泥壓力板尺寸、顏(yan)色明顯不一致的(de),要單獨(du)碼(ma)放(fang),以便退(tui)還(huan)給廠家,如有裂紋(wen)、缺(que)棱掉(diao)角的(de),要修理(li)后再(zai)用,嚴重的(de)不得使用。還(huan)要注意纖(xian)維(wei)(wei)水(shui)泥壓力板堆放(fang)場地(di)要平整,墊(dian)10cm×10cm通長方(fang)(fang)木,讓其高(gao)出地(di)面8cm以上(shang),方(fang)(fang)木上(shang)最好(hao)釘上(shang)橡(xiang)膠條(tiao),讓纖(xian)維(wei)(wei)水(shui)泥壓力板按75°立放(fang)斜靠(kao)在專用的(de)鋼架上(shang),每塊纖(xian)維(wei)(wei)水(shui)泥壓力板之間要用塑(su)料薄(bo)膜隔開靠(kao)緊碼(ma)放(fang),防止粘在一起和傾(qing)斜。
3、纖維水泥壓力板準備
首先用比色法對纖(xian)維水(shui)(shui)泥(ni)壓(ya)力(li)板的顏(yan)(yan)色進行(xing)挑選(xuan)分(fen)類;整個中庭部位纖(xian)維水(shui)(shui)泥(ni)壓(ya)力(li)板的顏(yan)(yan)色應(ying)一致,并根據設計(ji)尺(chi)寸(cun)和圖(tu)紙要求,將干(gan)掛纖(xian)維水(shui)(shui)泥(ni)壓(ya)力(li)板配套鋁(lv)掛件(jian)安(an)裝(zhuang)在背(bei)面(mian),按(an)照每塊(kuai)板材背(bei)面(mian)6個鋁(lv)掛件(jian)(最大板材截面(mian)尺(chi)寸(cun)為2780×1220mm)。為保證鋁(lv)掛件(jian)位置準(zhun)確垂直(zhi),事先在纖(xian)維水(shui)(shui)泥(ni)壓(ya)力(li)板背(bei)面(mian)按(an)照橫龍骨豎向間距600mm及纖(xian)維水(shui)(shui)泥(ni)壓(ya)力(li)板長(chang)(chang)度(du)等分(fen)尺(chi)寸(cun)彈十(shi)(shi)字(zi)交叉(cha)線,在十(shi)(shi)字(zi)交叉(cha)點上固定配套鋁(lv)扣件(jian),鋁(lv)掛件(jian)采用10mm長(chang)(chang),4mm粗不銹(xiu)鋼螺釘(ding)固定在纖(xian)維水(shui)(shui)泥(ni)壓(ya)力(li)板背(bei)面(mian),鋁(lv)扣件(jian)安(an)裝(zhuang)完畢之后必須復核(he)其水(shui)(shui)平(ping)及垂直(zhi)度(du)。
4、基層準備
清(qing)(qing)理(li)預做干掛纖維(wei)水泥(ni)壓力(li)板(ban)飾面的基層表面,同(tong)時進行(xing)吊直、套方、找規矩,彈(dan)出垂直線和水平(ping)線。并根據設計圖紙和實際需要(yao)彈(dan)出安裝纖維(wei)水泥(ni)壓力(li)板(ban)龍(long)骨的位置線和分(fen)塊線。將墻體(ti)表邊塵土(tu)、污(wu)垢清(qing)(qing)掃干凈。
5、掛線
按設(she)計圖(tu)紙(zhi)要(yao)(yao)求,纖維水泥壓力板(ban)龍骨安(an)裝(zhuang)前要(yao)(yao)事先用經緯儀打出大角兩個面的(de)(de)(de)豎向控(kong)制線,最(zui)好(hao)彈在(zai)(zai)離大角20cm的(de)(de)(de)位(wei)置上(shang),以便隨時檢查垂直(zhi)掛(gua)(gua)(gua)線的(de)(de)(de)準確(que)性,保證(zheng)順(shun)利安(an)裝(zhuang)。豎向掛(gua)(gua)(gua)線宜(yi)用∮1.0-∮1.2的(de)(de)(de)鋼(gang)絲為好(hao),下(xia)邊沉鐵重量為8-10kg,上(shang)端(duan)掛(gua)(gua)(gua)在(zai)(zai)專(zhuan)用的(de)(de)(de)掛(gua)(gua)(gua)線角鋼(gang)架(jia)上(shang),角鋼(gang)架(jia)用膨(peng)脹螺(luo)栓固(gu)定在(zai)(zai)中庭南北大角的(de)(de)(de)頂端(duan),一(yi)定要(yao)(yao)掛(gua)(gua)(gua)在(zai)(zai)牢固(gu)、準確(que)、不易(yi)碰動的(de)(de)(de)地方,并要(yao)(yao)注意(yi)保護和經常(chang)檢查。并在(zai)(zai)控(kong)制線的(de)(de)(de)上(shang)、下(xia)做出標(biao)記。
6、龍骨安裝
預先用∮8脹栓在結構面上固定50×50×4角(jiao)(jiao)鋼(gang)(gang)(角(jiao)(jiao)鋼(gang)(gang)上帶可調(diao)節孔),角(jiao)(jiao)鋼(gang)(gang)及角(jiao)(jiao)鋼(gang)(gang)上50×50×3.5豎向(xiang)(xiang)方(fang)(fang)鋼(gang)(gang)管(guan)(guan)水平(ping)間(jian)距(ju)為800mm。豎向(xiang)(xiang)方(fang)(fang)鋼(gang)(gang)管(guan)(guan)安(an)(an)(an)裝(zhuang)時,必須通過(guo)從上往下(xia)吊的鋼(gang)(gang)線進行(xing)復核,以檢(jian)測(ce)(ce)其垂直度。方(fang)(fang)鋼(gang)(gang)管(guan)(guan)安(an)(an)(an)裝(zhuang)完畢之(zhi)后,安(an)(an)(an)裝(zhuang)連接角(jiao)(jiao)鋼(gang)(gang)及橫(heng)(heng)向(xiang)(xiang)鋁(lv)龍(long)(long)(long)骨(gu)(gu),橫(heng)(heng)向(xiang)(xiang)鋁(lv)龍(long)(long)(long)骨(gu)(gu)豎向(xiang)(xiang)間(jian)距(ju)為600mm。角(jiao)(jiao)鋼(gang)(gang)與方(fang)(fang)鋼(gang)(gang)管(guan)(guan)及橫(heng)(heng)龍(long)(long)(long)骨(gu)(gu)之(zhi)間(jian)連接均采用∮10螺栓。龍(long)(long)(long)骨(gu)(gu)安(an)(an)(an)裝(zhuang)完之(zhi)后用紅外(wai)線水平(ping)儀檢(jian)測(ce)(ce)橫(heng)(heng)向(xiang)(xiang)鋁(lv)龍(long)(long)(long)骨(gu)(gu)是否(fou)水平(ping),掉鋼(gang)(gang)線檢(jian)測(ce)(ce)其是否(fou)垂直,過(guo)程中(zhong)發現問題及時調(diao)整,將誤差(cha)控制在最小。
7、面板安裝
將(jiang)事先加工好(hao)的面板(ban)(ban)按(an)照設計院提供的排版圖(tu)懸(xuan)掛(gua)(gua)于龍(long)骨(gu)之上(shang),面板(ban)(ban)與龍(long)骨(gu)間用干掛(gua)(gua)纖(xian)維(wei)水(shui)泥壓(ya)力(li)板(ban)(ban)配(pei)套鋁(lv)(lv)掛(gua)(gua)件(jian)連(lian)接,先將(jiang)同一(yi)水(shui)平層(ceng)(ceng)纖(xian)維(wei)水(shui)泥壓(ya)力(li)板(ban)(ban)輕掛(gua)(gua)在龍(long)骨(gu)上(shang),通(tong)過上(shang)下貫(guan)通(tong)鋼(gang)線及水(shui)平通(tong)線先調整好(hao)面板(ban)(ban)的水(shui)平與垂直度,再檢查板(ban)(ban)縫,板(ban)(ban)縫寬應按(an)設計要(yao)求(qiu),板(ban)(ban)縫寬度均勻,滿足要(yao)求(qiu)后,將(jiang)配(pei)套鋁(lv)(lv)掛(gua)(gua)件(jian)上(shang)的20mm長,6mm粗不銹鋼(gang)螺絲擰緊后進行(xing)上(shang)層(ceng)(ceng)板(ban)(ban)材安裝。
8、板縫處理
按照設計(ji)圖紙意圖,東側(ce)整面墻體(ti)纖維(wei)水泥壓力板(ban)板(ban)縫(feng)不做任何處理,采取明縫(feng)留(liu)設(豎縫(feng)寬20mm,橫縫(feng)寬10mm)。為此(ci)就要(yao)求在之前的(de)施工過程中必須加強縫(feng)的(de)水平、垂(chui)直檢測、確保橫平豎直。
9、獨立柱處理
獨立(li)柱轉(zhuan)角(jiao)(jiao)處(chu)陽角(jiao)(jiao)采用(yong)45°倒角(jiao)(jiao)對(dui)拼,打磨光滑,柱朝(chao)向走(zou)廊(lang)部位結構(gou)面采用(yong)滿(man)粘法(fa)。45°斜角(jiao)(jiao)對(dui)拼縫(feng)隙采用(yong)纖(xian)維(wei)水泥(ni)壓力板(ban)粉(fen)末加(jia)膠填縫(feng),外刷兩遍(bian)纖(xian)維(wei)水泥(ni)壓力板(ban)專(zhuan)用(yong)涂料。縫(feng)隙處(chu)壓力板(ban)粉(fen)末填縫(feng)時要注(zhu)意填縫(feng)均勻、飽滿(man)。
10、清理表面,刷置面劑
用棉(mian)絲將(jiang)纖維水泥壓力(li)板擦(ca)凈,若(ruo)有(you)膠或(huo)其(qi)他粘(zhan)結牢固(gu)的雜(za)物(wu),可用開(kai)刀(dao)輕(qing)輕(qing)鏟(chan)除(chu),用棉(mian)絲沾(zhan)(zhan)丙酮擦(ca)至干凈。罩面劑(ji)按(an)配(pei)合比在刷(shua)(shua)前半小時(shi)對好,注意區別底漆(qi)和面漆(qi),最好分階(jie)段(duan)操作。配(pei)置(zhi)罩面劑(ji)要(yao)(yao)攪勻,防止成膜時(shi)不(bu)勻。涂刷(shua)(shua)時(shi)要(yao)(yao)用羊(yang)毛刷(shua)(shua),沾(zhan)(zhan)漆(qi)不(bu)宜過多,防止流劑(ji),盡量少回刷(shua)(shua),以免(mian)有(you)刷(shua)(shua)痕,要(yao)(yao)求無氣泡、不(bu)漏刷(shua)(shua),刷(shua)(shua)的平整要(yao)(yao)有(you)光(guang)澤(ze)。
二、水泥外墻掛板安裝注意事項
1、在用水泥纖維外墻掛板做吊頂(ding)板(ban)時,主要配(pei)以輕(qing)鋼龍(long)骨、木龍(long)骨骨架(jia)等,由于該板(ban)板(ban)面平(ping)整、光潔,故嚴格要求龍(long)骨骨架(jia)安裝平(ping)整穩固定。
2、使用螺(luo)釘的(de)(de)規格應根據選(xuan)用龍骨的(de)(de)種類、規格決定(ding),并根據選(xuan)用水泥纖維外墻掛板的(de)(de)厚(hou)度,由(you)設計人員確定(ding)螺(luo)釘的(de)(de)直徑與(yu)長度。
3、在對水泥纖維外墻(qiang)掛(gua)板(ban)板(ban)面(mian)(mian)進(jin)行噴、涂、貼(tie)各種裝飾面(mian)(mian)層材料前,必須用砂紙或手(shou)提式平面(mian)(mian)磨光機(ji)清除板(ban)面(mian)(mian)上的(de)塵土油垢,嚴禁將保管不當,經過(guo)雨淋(lin)水浸未進(jin)行適(shi)當干燥處理的(de)潮濕板(ban)使用,以(yi)防板(ban)材扭曲(qu)變形(xing)。
4、對水(shui)泥纖(xian)維(wei)外墻掛板吊頂、隔(ge)墻的(de)安裝均應(ying)當在(zai)其它管(guan)線(xian)、風道工序完成后進行,以避免(mian)工人進入踩踏龍骨變形造成被刮的(de)嵌縫膩子開裂。
5、纖維水(shui)泥外墻板(ban)安裝前(qian),凡需對(dui)大幅面(mian)(mian)纖維水(shui)泥壓力平(ping)板(ban)進行(xing)噴、涂(tu)加工(gong)時,第一(yi)(yi)道(dao)封底涂(tu)料應進行(xing)板(ban)的雙面(mian)(mian)噴涂(tu),對(dui)已(yi)安裝固定的平(ping)板(ban)可(ke)直接在墻面(mian)(mian)單面(mian)(mian)噴涂(tu),但第一(yi)(yi)道(dao)封底漆(qi)必須為白色(se),才能使面(mian)(mian)層涂(tu)料反應出更好的色(se)彩。
以(yi)上(shang)就是水泥外墻掛(gua)板(ban)安裝須知,具體請參照(zhao)施工流(liu)程規(gui)范和(he)驗收規(gui)范。