裝修經驗總結 施工工期(qi)合理(li)安排
不同(tong)房型、面(mian)積(ji)和施工內容,所需要的(de)工期(qi)是不同(tong)的(de),總的(de)來(lai)說油工活比較耗時,也不宜(yi)太趕。普(pu)通工期(qi)應控制(zhi)在45天內為宜(yi),一般的(de)兩房平層40天能夠完成(cheng),但也不是很寬(kuan)裕,要安排好工序和主(zhu)材(cai)。
據了解(jie),裝修一套140—150平米的(de)三居(ju)室房(fang)子(zi),從開始到(dao)完工大(da)約需(xu)(xu)45天。面(mian)積較小的(de)兩(liang)居(ju)小戶型(xing)可節省四五天,而200多平米的(de)復式戶型(xing)則需(xu)(xu)多用(yong)四五天。房(fang)屋裝修過程可分為三個(ge)階段(duan):前期(qi)(qi)、中期(qi)(qi)和后期(qi)(qi)。
裝(zhuang)(zhuang)修(xiu)(xiu)前期(qi)的(de)工作(zuo)主(zhu)要(yao)(yao)(yao)是(shi)裝(zhuang)(zhuang)修(xiu)(xiu)設(she)計(ji),從選(xuan)定(ding)裝(zhuang)(zhuang)修(xiu)(xiu)公司到(dao)確(que)定(ding)設(she)計(ji)方案,需10—15天(tian)。在這段(duan)時間里,顧客還(huan)要(yao)(yao)(yao)選(xuan)好(hao)裝(zhuang)(zhuang)修(xiu)(xiu)所用(yong)主(zhu)要(yao)(yao)(yao)材料,尤(you)其是(shi)瓷磚和櫥(chu)(chu)柜。因為櫥(chu)(chu)柜一(yi)般都是(shi)定(ding)制(zhi)的(de),需要(yao)(yao)(yao)20—35天(tian)才(cai)能(neng)完(wan)成。專業櫥(chu)(chu)柜設(she)計(ji)師(shi)還(huan)要(yao)(yao)(yao)根據實際情(qing)況對廚房進行(xing)設(she)計(ji),如確(que)定(ding)水(shui)電(dian)路的(de)位(wei)置,以便開(kai)工后(hou)及時進行(xing)水(shui)電(dian)改造。瓷磚則是(shi)開(kai)工后(hou)最先用(yong)到(dao)的(de),所以在裝(zhuang)(zhuang)修(xiu)(xiu)前期(qi),一(yi)定(ding)要(yao)(yao)(yao)先選(xuan)好(hao)櫥(chu)(chu)柜和瓷磚。
裝(zhuang)(zhuang)修(xiu)(xiu)中期(qi)(qi)主要是(shi)施(shi)工(gong)(gong)(gong)(gong)期(qi)(qi)。開工(gong)(gong)(gong)(gong)后(hou)(hou),水(shui)電(dian)工(gong)(gong)(gong)(gong)和(he)木(mu)(mu)工(gong)(gong)(gong)(gong)先(xian)進(jin)(jin)場(chang)(chang)施(shi)工(gong)(gong)(gong)(gong)。水(shui)電(dian)路(lu)改(gai)造需(xu)(xu)要4天(tian)(tian)(tian)到(dao)(dao)一周(zhou)的時(shi)(shi)間(jian)(jian)(jian),木(mu)(mu)工(gong)(gong)(gong)(gong)做吊(diao)(diao)頂(ding)、背景(jing)墻(qiang)、現場(chang)(chang)制作柜子等(deng)(deng)需(xu)(xu)要15天(tian)(tian)(tian)左(zuo)右(you)。大約7天(tian)(tian)(tian)后(hou)(hou)水(shui)電(dian)路(lu)改(gai)造完(wan)(wan)成,瓦工(gong)(gong)(gong)(gong)開始進(jin)(jin)場(chang)(chang)鋪瓷磚。先(xian)鋪廚(chu)(chu)房和(he)衛生間(jian)(jian)(jian),最(zui)后(hou)(hou)再(zai)鋪公(gong)共(gong)(gong)部分,整個過程(cheng)持(chi)續到(dao)(dao)第(di)30天(tian)(tian)(tian)左(zuo)右(you)。第(di)15天(tian)(tian)(tian)左(zuo)右(you),木(mu)(mu)工(gong)(gong)(gong)(gong)完(wan)(wan)成工(gong)(gong)(gong)(gong)作,油工(gong)(gong)(gong)(gong)開始進(jin)(jin)場(chang)(chang),進(jin)(jin)行墻(qiang)體刮(gua)膩子找平、木(mu)(mu)作和(he)墻(qiang)面的刷(shua)漆等(deng)(deng)工(gong)(gong)(gong)(gong)作,要持(chi)續到(dao)(dao)裝(zhuang)(zhuang)修(xiu)(xiu)完(wan)(wan)工(gong)(gong)(gong)(gong)前兩三天(tian)(tian)(tian)。在(zai)這段時(shi)(shi)間(jian)(jian)(jian)里,您可(ke)以(yi)到(dao)(dao)市(shi)場(chang)(chang)上(shang)找找喜歡(huan)的家具。以(yi)上(shang)施(shi)工(gong)(gong)(gong)(gong)完(wan)(wan)成后(hou)(hou),剩(sheng)下的就(jiu)基本(ben)上(shang)是(shi)裝(zhuang)(zhuang)修(xiu)(xiu)的后(hou)(hou)期(qi)(qi)工(gong)(gong)(gong)(gong)程(cheng),這時(shi)(shi)候離裝(zhuang)(zhuang)修(xiu)(xiu)完(wan)(wan)工(gong)(gong)(gong)(gong)還剩(sheng)兩三天(tian)(tian)(tian)的時(shi)(shi)間(jian)(jian)(jian),木(mu)(mu)工(gong)(gong)(gong)(gong)回來安裝(zhuang)(zhuang)窗簾桿、五金掛件等(deng)(deng)。在(zai)廠家訂購的地板(ban)、門、潔具、櫥柜等(deng)(deng)也開始陸續安裝(zhuang)(zhuang),還要進(jin)(jin)行廚(chu)(chu)房和(he)衛生間(jian)(jian)(jian)的吊(diao)(diao)頂(ding)(廚(chu)(chu)衛吊(diao)(diao)頂(ding)與公(gong)共(gong)(gong)部分不同,需(xu)(xu)后(hou)(hou)期(qi)(qi)再(zai)吊(diao)(diao)),這些(xie)工(gong)(gong)(gong)(gong)作比較(jiao)簡單快(kuai)捷,每種只需(xu)(xu)1天(tian)(tian)(tian)左(zuo)右(you)時(shi)(shi)間(jian)(jian)(jian),全(quan)部完(wan)(wan)工(gong)(gong)(gong)(gong)共(gong)(gong)需(xu)(xu)3天(tian)(tian)(tian)左(zuo)右(you)。
大致工期安(an)排情況(kuang)如(ru)下:
1、開工(gong)前至少10天:做設計定方案(an);選(xuan)定裝(zhuang)修公司,提出裝(zhuang)修內容和要求;實地測量有關數據,繪(hui)制詳細圖紙;與設計師全面(mian)溝通,確定最終方案(an)。
2、開工前(qian)至少5天:看預(yu)算(suan)簽合(he)同;確定所(suo)要使用(yong)的材料;自己對家裝(zhuang)費(fei)用(yong)進行初步(bu)預(yu)算(suan),同家裝(zhuang)公(gong)司(si)的預(yu)算(suan)進行比較;簽定裝(zhuang)修合(he)同。
3、開工前至少2天(tian):進(jin)場(chang)前做準備;與物業(ye)部門聯系,完成必要的手續;和鄰居(ju)打好招呼;門窗(chuang)材(cai)料(liao)(liao)及輔(fu)助材(cai)料(liao)(liao)進(jin)場(chang);交施工方鑰匙;付(fu)首期裝修款(kuan)。
4、開工后1-2天(tian):敲墻體改結構。
5、開工(gong)(gong)5-10天:安(an)水管裝(zhuang)電(dian)路;管線材(cai)料處理(li)驗收;隱(yin)蔽工(gong)(gong)程(cheng)驗收。
6、開(kai)工后10-20天: 鋪(pu)瓷磚做墻(qiang)面;泥瓦工程驗收;驗收墻(qiang)面材(cai)料,比(bi)如墻(qiang)面漆、瓷磚等。
7、開工20-30天:做木(mu)工涂油漆(qi);油漆(qi)材(cai)料進場驗(yan)收;木(mu)工項目驗(yan)收。
8、開工30-50天:鋪地(di)(di)板做廚衛裝設備;地(di)(di)板材(cai)料驗(yan)收(shou)(shou);櫥柜到(dao)(dao)場(chang)安(an)裝驗(yan)收(shou)(shou);衛浴(yu)產品(pin)到(dao)(dao)場(chang)安(an)裝驗(yan)收(shou)(shou);買回電器并安(an)裝;衛浴(yu)產品(pin)到(dao)(dao)場(chang)安(an)裝驗(yan)收(shou)(shou)。
9、開工50-60天:搞驗(yan)收做(zuo)決算(suan);進(jin)行總結算(suan)。